Bid bond vs performance bond vs payment bond: when contractors need each (2026)
The three core construction bonds explained — who's protected, when each is required, what each costs, and what happens on a claim.
Updated June 2026 · BettrBonds — Contract surety for SE contractors
Short answer
Bid bonds guarantee a winning bidder accepts the contract (protects the owner during procurement, ~5-10% of bid value, usually no premium). Performance bonds guarantee project completion per contract specs (protects the owner during construction, 100% of contract value, 0.75%-3% premium). Payment bonds guarantee subs, suppliers, and laborers get paid (protects them, 100% of contract value, usually bundled with performance bond at no extra premium). Public construction over $150,000 typically requires all three.
Side-by-side: what each bond does
Bid bond
Performance bond
Payment bond
Who's protected
Project owner (during bidding)
Project owner (during construction)
Subs, suppliers, laborers
When required
Bid submission
Contract award + construction
Same as performance bond
Typical amount
5-10% of bid value
100% of contract value
100% of contract value
Typical premium
$0 to $250 fee
0.75% – 3% of contract
Bundled with performance bond
What triggers a claim
Winning bidder refuses to sign
Contractor abandons or fails to complete
Contractor fails to pay sub/supplier
Maximum payout
Difference between this bid and next lowest, capped at bond amount
Bond amount (cost to complete)
Bond amount (unpaid amounts)
Federal requirement
Most public projects, varies by procurement
Miller Act: contracts over $150K
Miller Act: contracts over $150K
Bid bonds: protecting the project owner during procurement
When a contractor submits a bid on a construction project, the project owner needs assurance that if the contractor wins, they'll actually accept the contract at the bid price. Contractors sometimes "bid low and walk" — they win the bid, then refuse to sign because they realize the project is unprofitable. The bid bond covers the owner's cost of going to the next lowest acceptable bidder.
Bid bond mechanics:
Required on most public construction projects (federal, state, municipal, school)
Required on many large private commercial projects (over $1M)
Amount is a percentage of the bid: federal commonly 5%, state DOT often 5-10%, large private 5-10%
Typically NO premium charged — sureties issue bid bonds as a courtesy because they want to write the performance bond if the contractor wins
Small underwriting fee may apply ($100-$250) per bid bond
If the contractor wins the bid AND signs the contract AND posts the performance bond, the bid bond is released
Performance bonds: protecting the owner during construction
Performance bonds guarantee that if the contractor abandons the project, goes bankrupt, or fails to perform, the surety will:
Complete the project with a takeover contractor approved by the owner, OR
Pay another contractor to complete the project, OR
Pay the owner the cost of completion up to the bond amount
Performance bond mechanics:
Required on virtually all public construction over $150K (federal Miller Act, state Little Miller Acts)
Required on most large private commercial, school, hospital, federal facility projects
Amount is typically 100% of contract value; complex projects sometimes 110%
Premium is paid up front and is non-refundable except on contract reduction
Surety's exposure runs until project completion + warranty period (typically 1 year)
Payment bonds: protecting subs, suppliers, and laborers
Payment bonds guarantee that subcontractors, material suppliers, and laborers on the project get paid even if the prime contractor fails to pay them. Without a payment bond, unpaid subs typically file mechanic's liens against the property — but federal property cannot be liened, which is why federal projects require payment bonds. State and private projects often require payment bonds to prevent mechanic's liens.
Payment bond mechanics:
Required on Miller Act projects (federal over $150K) and most Little Miller Act projects (state)
Required on many private projects where owner wants to prevent mechanic's liens
Amount is typically 100% of contract value
Usually bundled with the performance bond as a combined "P&P bond" — same form, same surety, ONE premium covers both
Standalone payment bonds (when required without performance bond) cost about 1-2.5% of contract value
Claims can be filed by first-tier subs/suppliers (direct contract with prime) and sometimes second-tier (sub's sub) depending on bond terms and state law
What happens when a claim is filed
The surety bond claim process is fundamentally different from an insurance claim:
Claim is filed with the surety by the protected party (owner for performance bond, sub/supplier for payment bond)
Surety investigates — reviews the contract, the claim, the contractor's response, project records, any partial completion
Surety decides — pay the claim (up to bond amount), arrange completion, or deny
If surety pays, the contractor is required to reimburse the surety in FULL under the indemnity agreement signed when the bond was issued
Surety can pursue collection against the contractor (corporate assets) AND against the individual indemnitors (personal assets) — typically including the owner's home, savings, retirement
This is why a surety claim is far more severe than an insurance claim. Insurance pays without reimbursement. Surety pays then collects from the contractor. A single claim against your bonding history also damages your ability to get bonded going forward — many sureties decline contractors with any prior loss.