· Back to BettrBonds

Bid bond vs performance bond vs payment bond: when contractors need each (2026)

The three core construction bonds explained — who's protected, when each is required, what each costs, and what happens on a claim.

Updated June 2026 · BettrBonds — Contract surety for SE contractors

Short answer
Bid bonds guarantee a winning bidder accepts the contract (protects the owner during procurement, ~5-10% of bid value, usually no premium). Performance bonds guarantee project completion per contract specs (protects the owner during construction, 100% of contract value, 0.75%-3% premium). Payment bonds guarantee subs, suppliers, and laborers get paid (protects them, 100% of contract value, usually bundled with performance bond at no extra premium). Public construction over $150,000 typically requires all three.

Side-by-side: what each bond does

Bid bondPerformance bondPayment bond
Who's protectedProject owner (during bidding)Project owner (during construction)Subs, suppliers, laborers
When requiredBid submissionContract award + constructionSame as performance bond
Typical amount5-10% of bid value100% of contract value100% of contract value
Typical premium$0 to $250 fee0.75% – 3% of contractBundled with performance bond
What triggers a claimWinning bidder refuses to signContractor abandons or fails to completeContractor fails to pay sub/supplier
Maximum payoutDifference between this bid and next lowest, capped at bond amountBond amount (cost to complete)Bond amount (unpaid amounts)
Federal requirementMost public projects, varies by procurementMiller Act: contracts over $150KMiller Act: contracts over $150K

Bid bonds: protecting the project owner during procurement

When a contractor submits a bid on a construction project, the project owner needs assurance that if the contractor wins, they'll actually accept the contract at the bid price. Contractors sometimes "bid low and walk" — they win the bid, then refuse to sign because they realize the project is unprofitable. The bid bond covers the owner's cost of going to the next lowest acceptable bidder.

Bid bond mechanics:

Performance bonds: protecting the owner during construction

Performance bonds guarantee that if the contractor abandons the project, goes bankrupt, or fails to perform, the surety will:

  1. Complete the project with a takeover contractor approved by the owner, OR
  2. Pay another contractor to complete the project, OR
  3. Pay the owner the cost of completion up to the bond amount

Performance bond mechanics:

Payment bonds: protecting subs, suppliers, and laborers

Payment bonds guarantee that subcontractors, material suppliers, and laborers on the project get paid even if the prime contractor fails to pay them. Without a payment bond, unpaid subs typically file mechanic's liens against the property — but federal property cannot be liened, which is why federal projects require payment bonds. State and private projects often require payment bonds to prevent mechanic's liens.

Payment bond mechanics:

What happens when a claim is filed

The surety bond claim process is fundamentally different from an insurance claim:

  1. Claim is filed with the surety by the protected party (owner for performance bond, sub/supplier for payment bond)
  2. Surety investigates — reviews the contract, the claim, the contractor's response, project records, any partial completion
  3. Surety decides — pay the claim (up to bond amount), arrange completion, or deny
  4. If surety pays, the contractor is required to reimburse the surety in FULL under the indemnity agreement signed when the bond was issued
  5. Surety can pursue collection against the contractor (corporate assets) AND against the individual indemnitors (personal assets) — typically including the owner's home, savings, retirement

This is why a surety claim is far more severe than an insurance claim. Insurance pays without reimbursement. Surety pays then collects from the contractor. A single claim against your bonding history also damages your ability to get bonded going forward — many sureties decline contractors with any prior loss.

Get a quote on bid, performance, and payment bonds →